TBTS Logo UpdateTBTS Logo UpdateTBTS Logo UpdateTBTS Logo Update
  • Home
  • Education
    • Community Traffic Safety Teams (CTST)
      • Hillsborough CTST
      • Pasco CTST
      • Pinellas CTST
      • West Central CTST
      • The Tampa Bay Area University CTST
    • Safety Academy (LATSA)
    • Safety Summit
    • IPTM Tuition-Free Courses
  • Engineering
    • FDOT Active Projects
    • Safety Engineering
    • Access Management
    • Design Build Push Button (DBPB)
    • High Friction Surface Treatment Program (HFST)
    • Highway Safety Improvement Program (HSIP) ​
  • Community Events
  • FDOT District 7 Safety Newsletter
  • Blog
  • Contact
✕
Target Zero Fatalities & Serious Injuries
July 9, 2021
Highway Safety Improvement Program (HSIP) ​
July 19, 2021
Published by Benesch on July 19, 2021
Categories
  • Engineering
Tags
  • Design-Build
  • funding
  • guide
  • intersections
  • Push Button Contract
  • safety

Design-Build Push Button Contract Significantly Reduces the Time It Takes to Implement Safety Improvements – Florida

In the past, Florida DOT (FDOT) has used its traditional Work Program Process to deliver safety improvements using FHWA safety funds; this brought concepts to construction within a 3 to 5 year time frame.
FDOT District 7 (D7; offices located in Tampa) decided that some ‘simple or low cost’ safety concepts did not need to go through the full work program process and could be expedited. In an attempt to reduce the time frame from concept to construction and to simplify the process for safety improvements, Florida DOT District 7 worked with the FHWA Florida Division and developed a push button framework using Federal safety funds.

Ultimately, the push button framework allowed the District to reduce the time it takes to deliver simple or low cost safety improvement from 3-5 years to 3-9 months.

By expediting the delivery of safety improvements, FDOT is also able to reduce the number of crashes that could have occurred while the concept is being developed, helping FDOT to achieve the FHWA Every Day Counts (EDC) goal. Furthermore, by achieving a crash reduction within a few months, as opposed to years, the project's Net Present Value (NPV) is increased due to the time, value, money. NPV is the methodology that FDOT uses to select and prioritize safety engineering projects.

The key challenges surrounded developing a framework that allowed FDOT to:
  • Meet Federal guidelines to obtain the approval of funds.
  • Meet internal requirements related to scheduling, coordination, QA/QC, etc.
  • Eliminate internal barriers that had stove-piped the work in order to create a streamlined schedule.
Design-Build Push Button Contract
To meet the challenge, D7 put into place a design-build push button contract, which was approved by the FHWA Florida Division & FHWA Headquarters.
  • D7 identifies a need for a simple or low cost safety improvement.
  • D7 generates a task cost estimate using pre-approved contract pay items and corresponding unit prices.
  • D7 submits the cost estimate along with the task's scope of services and National Environmental Policy Act (NEPA) categorical exclusion certification to the FHWA Florida Division for approval through the Federal Financial Management Information System (FMIS).
  • The FHWA Florida Division reviews the task for eligibility criteria, and if eligible, approves it through FMIS.
  • D7 encumbers Federal safety funds and issues a notice to proceed for the task work order.
  • The design-build team delivers a constructed concept within 3-9 months (depending on difficulty and work load)
Design-Build Push Button Contract
Through the use the DBPB, D7 is able to complete much faster delivery/construction of ‘simple or low cost’ safety improvements. Safety improvements delivered through this contract include the installation of:
  • High emphasis crosswalks
  • Bicycle lanes
  • Pavement markings, wet weather audible marking
  • Concrete medians
  • Overhead sign structures
  • Turn lanes or offset left turn lanes
  • Pedestrian safety treatment - Rectangular Rapid-Flashing Beacons (RRFBs)
  • New traffic signal installations
  • High friction surface treatments

Multiple roads benefited from this contract, in total, the first design-build push button contract had 55 projects for the 24-month contract period.

Design-Build Push Button Contract
What technical and/or institutional changes resulted from the new practice?
  • Buy-in from FDOT and FHWA management for the need to create this innovative contract
  • Approval from FHWA to allow Federal-funded safety projects to be implemented at the District level using this design-build push button contract format
  • Contract process changes for FDOT design-build contract to accommodate this innovative approach
  • Creation of statewide design-build push button contract task team
What benefits were realized as a result of the practice?
  • Reduced the time it takes to implement a safety improvement; at the same time, reduced the potential for fatalities and serious injuries during the shortened implementation period
  • Reduced overall costs of the project application process by reducing the turnover rate
  • Ensured compliance with Federal guidelines on all submitted project proposals
  • Promoted use of these low-cost safety improvements

Design Build Push Button 3

Contract Evaluation Documents
Chapter 1 - Concept Development
Click here to download the files.
Chapter 2 - Contract Process
Click here to download the files.
Chapter 3 - RFP Scope
Click here to download the files.
Chapter 4 - Technical Proposal
Click here to download the files.
Chapter 5 - Technical Proposal Evaluation
Click here to download the files.
Chapter 6 - Design-Build Push Button Process
  • Chapter 6.1 - Design Clarification
  • Chapter 6.2 - Project Solve Website
  • Chapter 6.3 - Weekly Progress Meetings
  • Chapter 6.4 - Community Awareness
  • Chapter 6.5 - Electronic Review Comments
  • Chapter 6.6 - Final Design Plans
Chapter 7 - Before and After Photos
Click here to download the files.
Chapter 8 - Contract Evaluation
Click here to download the files.

Questions?

Peter Hsu, P.E.

FDOT District 7
District Special Programs Engineer
813.975.6251

ping.hsu@dot.state.fl.us

Share
1
Benesch
Benesch

Related posts

March 7, 2023

Pasco County Pedestrian Safety – PSA


Read more
January 8, 2023

FDOT District 7 Safety Newsletter


Read more
February 24, 2022

VITAL FEW


Read more

Comments are closed.

© 2021 Tampa Bay Traffic Safety | All Rights Reserved | Site Maintained by Tindale Oliver